Powered shell

The building foundation for your fit-out.

Bring your preferred fit-out and equipment strategy to a dedicated building with clearly defined campus and infrastructure interfaces.

Delivered condition

Understand the shell before planning the fit-out.

Powered shell can describe different delivered conditions. The useful question is exactly what will be complete, energized, tested, and handed over. ARX's proposed scope defines the building and infrastructure interfaces that support the customer-led work.

Scope

What the shell scope should define.

Powered shell scope areas
Scope areaWhat to define
Base buildingStructure, envelope, access, loading, and other agreed building provisions.
Power interfaceDelivery point, capacity basis, protection, metering, and remaining electrical work.
Mechanical interfaceAgreed cooling provisions, connection points, and customer fit-out responsibilities.
ConnectivityCampus pathways, entry arrangements, and service demarcations.
AcceptanceTests, records, defects process, and conditions for transfer.
OperationsWho maintains each system before, during, and after fit-out.

Coordination

Coordinate both delivery programs.

The campus works and customer fit-out must meet at the same technical boundary. Align design information, long-lead items, access dates, testing, and construction interfaces early enough to support the intended deployment.

Campus services

Pair physical control with selected campus services.

Connectivity coordination, access processes, and operating support can be evaluated alongside the shell. Services are defined for the project rather than assumed to accompany the building.

Define the shell and your fit-out boundary.

Email our team with your fit-out approach, building size, power requirement, and the work your team plans to deliver.